The Director for Corporate Services submitted a report to update the Committee on the progress of the schemes within the HRA Capital Programme to 31 July 2018.
The recommendation, as per the report, was moved by Councillor Higgins.
The motion was seconded by Councillor Glancy.
All Members were in favour.
RESOLVED that
(1) the Committee determines
the level of charges for 2019-20 for each of the services set out in the
attached table to operate from 1st April 2019;
(2) the Committee determines
the level of charges for the activities described at 3.12.3 for implementation
with effect from 1st October 2018 (commensurate with the
introduction of the new Regulations), as highlighted in Appendix A.
Publication date: 05/09/2018
Date of decision: 05/09/2018
Decided at meeting: 05/09/2018 - Place Committee