provide information on actual expenditure and income incurred on the Housing
Revenue Account (HRA), compared to the latest approved budget for the period 1 April
2023 to 30 June 2023 for revenue and capital budgets.
Cabinet:
1) NOTED the financial position on the HRA at 30 June 2023 and the year-end forecast for both revenue and capital.
2) APPROVED the increase to the overall value of the HRA capital programme to include £118k for the estimated expenditure on 3 fire damaged properties to be funded from insurance and a virement from another capital programme item.