Decision Maker: Policy, Finance and Administration Committee
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Director for Corporate Services submitted a report to
provide information on the provisional Capital Programme year end position for
2017-18, including a range of performance measures, and to give consideration
for requests for carrying forward unspent budgets in 2017-18 to 2018-19 in
respect of specific schemes.
The Chair explained that there is no choice but to replace
the finance system, the cost of which would be £250k and to do nothing would be
£400k. And that due to the upgrade, which would likely be a cloud based system
then the project would need to be funded from revenue funds which would
necessitate a draw from the Corporate Priorities Reserve. The Chair also
highlighted the procurement and implementation could be in conjunction with
other Councils.
The recommendations were moved by Councillor Orson and
Councillor Higgins seconded.
All Members were unanimously in favour.
RESOLVED
that:
1) the schemes in the 2017-18 Capital Programme totalling £1,842,000
and shown in the column headed “Amount to Carry Forward to 2018-19 Scheme
Specific” at Appendix A be carried forward and included in the Capital
Programme as funded schemes.
2) delegated authority be granted
to the Director for Corporate Services to vary the amount of the agreed carry
forward on any scheme subject to the spending on any scheme not exceeding the
total authorised funds for that scheme.
3) the project mandate relating to
a procurement of a new finance system for inclusion into the 2019-20 capital
programme for the sum of £250,000 as referred to in para 3.8 and attached at
Appendix B be approved.
Report author: Natasha Allsopp
Publication date: 19/04/2018
Date of decision: 11/04/2018
Decided at meeting: 11/04/2018 - Policy, Finance and Administration Committee
Accompanying Documents: