Decision Maker: Director for Housing and Communities
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
To extend the current contract to allow the contractor time to deliver the commissioned 35 days, and then the commission a further 20 days at the new daily rate of £450.
To also commission a further 9 days at a daily rate of £450 to provide additional capacity for the inspection. These additional days will be funded within the financial year 24/25.
1. To agree a further extension of the Consultancy Agreement on the following terms:-
(a) From 05.12.2023 to 14.05.2024 to undertake 35 days at an increased
daily rate of £450
(b) To undertake a further 20 days at a daily rate of £450 at approximately
3 days a
week.
(c) To provide additional capacity for the inspection by the Regulator for
Social
Housing – a further 9 days at a daily rate of £450 from the financial year
2024/25 with delegated authority from the Director for Housing and Communities
(Deputy Chief Executive)
(d) To enter into the necessary legal agreements to enable this change
2. To apply a contract procurement exemption to enable this change
3. To apply a General Exception Notice
4. For the Chief Finance Officer in consultation with the Director for
Housing and Communities and the Portfolio Holder for Housing &
Landlord Services to draw down £19,290 from HRA reserves to fund
both the increase in the daily rate and the commissioning of 20 further
days in 2023-24 and £4,050 to fund the commissioning of a further 9
days in 2024-25.
Urgent item?: Yes
Publication date: 17/04/2024
Date of decision: 17/04/2024