Decision details

Authority to draw upon Regeneration and Innovation Reserve

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

Following survey work undertaken on Christmas lights infrastructure it was identified that works would be required to take place to ensure compliance with relevant regulations. The cost of these works is £13,000.

As well as this, surveys were undertaken on the structural integrity of the Christmas tree pits at both Parkside offices and the town centre location. These surveys highlighted some health and safety issues so designs/works have had to be commissioned, at a cost of £1,100, to enable contractors to put in place the following solutions:

(1) A temporary solution requiring Kentledge (counterweight) in the
town centre due to time constraints (cost £12,900);


(2) A permanent solution for the provision of the Christmas Tree pit at
Parkside (cost £3,000)

Decision:

Authority for the Regeneration Manager to draw upon the Regeneration and Innovation reserve, to the value of up to £30,000, to ensure relevant works are undertaken to ensure compliance for Christmas lights and Tree

Alternative options considered:

Leave the required works - REJECTED - this would mean no Christmas lighting scheme would be able to be erected in Melton Town Centre and both Parkside and the town centre would not be able to erect Christmas trees this year. As a result of this it would be likely that the lights switch on event would not be able to take place

Publication date: 14/11/2019

Date of decision: 13/11/2019

Accompanying Documents: