38 GENERAL FUND REVENUE BUDGET 2025/26 AND MEDIUM TERM FINANCIAL STRATEGY 2026/27 TO 2028/29 PDF 166 KB
The report on the General Fund Revenue Budget 2025/26 and the Medium Term Financial Strategy 2026/27 to 2028/29 is to be presented to the Committee, prior to final consideration by Cabinet and Council in February 2025.
Please note that
Appendix E (Parish Council Precepts) is not available. This appendix will be
available for the Council meeting in February.
All appendices are
draft and are correct at the time of publication.
Additional documents:
Minutes:
The Director for
Corporate Services, Dawn Garton, introduced the report with a presentation.
In relation to the special expenses budget, the comment was raised as to
whether there are the funds available to purchase land to expand the cemetery.
In response it was noted that although expansion works would take place, there
currently isn’t a funded business case or definitive plan.
Concern was raised that by 2027/28, reserves would be exhausted and that
service reductions would need to be considered.
Concern was raised in
relation to the outstanding property service charge recharges. It was noted by
Officers that there are currently negotiations with tenants of Phoenix House
regarding this matter. Members asked that the updated position be provided to
all Members of the committee outside the meeting.
A query was raised as to
whether the Council could stick to the £306k budget for homelessness temporary
accommodation, considering that the current year spend is £348k. It was noted
that it is highlighted as a risk, however the Council has a duty to house
people. There has been increased demand, which has created a difficult
situation. Officers would review how assets could be utilised to support the
Council in delivering its statutory duty and Officers are confident that the
service would be delivered within budget.
A query was raised as to whether the Council could afford the Community
Coordinator role and the role in the Health and Active Communities Team. It was
clarified that both are growth items and it is proposed to be funded by UKSPF
funding. There would be an overview of outputs and an assessment of whether the
roles meet outcomes.
The question was raised as to whether it is worth taking on a Funding
Co-ordinator when, potentially, there is only two years left before Melton
Borough Council ceases to exist. In response, it was clarified that nothing has
yet been decided and the Council still has a duty to deliver services until a
time it doesn’t exist. The aim is that the post would be fixed term for two
years and would have to deliver within that time. It was noted that the Funding
Co-ordinator would have different focus from the previous Funding Co-ordinator
role.
Following a concern raised regarding the MMDR South, it was confirmed
that the Council are continuing to work with Leicestershire County Council
(LCC) but that LCC doesn’t see the project going ahead in either the short,
medium or long term. Despite this, there is still a commitment towards
delivering it and the local plan depends on the southern section of the road
being delivered.
A query was raised
regarding the one-off planning expenditure in relation to the solar farm
inquiry. In response, Officers confirmed that the expense is expected but that
that they are unsure what the exact figure would be. An estimate had been
included in the forecast reserves.
RESOLVED
That the report is NOTED
and Members’ comments are presented to Cabinet at the next Cabinet meeting.