Issue - meetings

Capital Programme Monitoring

Meeting: 05/09/2018 - Place Committee (Item 25)

25 HRA Capital Programme Monitoring pdf icon PDF 77 KB

The Director of Corporate Services to submit a report to update the Committee on the progress of schemes within the HRA Capital Programme to 31 July 2018.

Additional documents:

Minutes:

The Director for Corporate Services submitted a report to update the Committee on the progress of the schemes within the HRA Capital Programme to 31 July 2018.

 

The recommendation, as per the report, was moved  by Councillor Higgins.

 

The motion was seconded by Councillor Glancy.

 

All Members were in favour.

 

RESOLVED that

 

(1)  the Committee determines the level of charges for 2019-20 for each of the services set out in the attached table to operate from 1st April 2019;

 

(2)  the Committee determines the level of charges for the activities described at 3.12.3 for implementation with effect from 1st October 2018 (commensurate with the introduction of the new Regulations), as highlighted in Appendix A.