The Corporate Director to submit a report to update the Committee on the progress of schemes within the Capital Programme to 31st July 2017.
Minutes:
The Corporate Director submitted a report to provide
information on actual expenditure and income incurred on this Committee’s
services compared to the latest approved budget for the period 1st April 2017
to 30th June 2017.
The Central Services Manager gave an overview of the report,
bringing Members attention to:
•Appendix A of the report showing the Capital Programme
Progress Report 2017/18– Jul 2017.
•5.2 of the report noting the General Expenses underspend of
£27,000.
•5.3 of the report noting the forecast is generally in line
with the budget with schemes progressing although much expenditure has yet to
be incurred. The three exceptions to this are: The Disabled Facilities Grants,
which is expected that there will be an underspend against budget of £67k for
which alternative uses are being explored. However, it is difficult to predict
given the changes due to come in October regarding lightbulb. The Warm Homes
Grant budget will be reduced by £10k as part of the budget setting process
later in the year to reflect the refund of a repayment of a grant from 2016/17
which was partially funding the budget in 2017/18. The Central Services Manager
paid particular attention to the third exception which was Tenders in relation
to the Public Conveniences project; these have been received and evaluated with
the anticipated costs of the main contract and other associated costs being
£50k over budget. Members were asked to consider either increasing the
programme or developing only one of the two sites (likely Wilton Road) and are
asked to instruct officers as per recommendation 2.3.
A Discussion was had regarding Housing stock in regards to
whether they have all had full electric checks, as a Member had read a report
stating they have not.
The Head of Communities and Neighbourhoods noted that the
performance information related to re-wiring and not the statutory checks the
council has to undertake, these are carried out and the council has over 99%
access and is progressing those properties they cannot access.. It was also
noted that a full re wiring contract is being procured which would
significantly improve the decent homes performance.
A Member enquired as to whether the work which is starting
on Beckmill will involve cladding and sprinklers, to which the Head of
Communities and Neighbourhoods noted that neither Granby House nor Beckmill
court will have AMC cladding. With regards to sprinklers, there are no
properties over three floors that require sprinklers. A Member noted that a MBC
officer had told them that there would be cladding at Beckmill, which may want
to be looked into. The Head of Communities & Neighbourhoods assured the
Committee that specifications for the project had been reviewed to ensure they
met all standards.
A Member noted that the Park Lane public convenience site
would have more potential value if it receives planning permission.
A brief discussion took place regarding the Fairmead
regeneration project with the Head of Communities and Neighbourhoods noting
that this project is re starting and expecting delivery to start in 2018/19,
and that it is potentially a 2 year
project.
The Chair sought a proposer and seconder to move the recommendations. All Members were in favour.
RESOLVED that
(1)The progress made on each capital scheme and that the capital programme will be amended as part of the budget setting process as outlined in sections 5.3 and 5.4 be noted by Members.
(2)The revised HRA capital programme under the Head of Communities and Neighbourhoods delegation as detailed in paragraph 5.4 be noted by Members.
(3)Members recommend a supplementary estimate to the Policy, Finance & Administration Committee for approval of £50,000 to be funded from capital receipts in order to progress the Public Conveniences Project for the construction of two new facilities.
Supporting documents: