The Chief Internal Auditor to submit a report to
update Members on
the progress made in delivering the 2021/22
Internal Audit Plan and
key findings arising from audit assignments completed.
Minutes:
Rachel
Ashley-Caunt, Chief Internal Auditor introduced the
report updating Members on the progress made in delivering the 2021/22 Internal
Audit Plan and key findings arising from audit assignments completed.
Ms.
Ashley-Caunt highlighted the Internal Audit Progress
Report at Appendix A, which set out all assignments within the current year's
Internal Audit Plan, the status of the assignments as at the time of reporting
and the outcomes of the assignments which had been completed. Good progress against delivery of the
Internal Audit Plan had been made, with good outcomes and the positive
assurance opinions should provide reassurance to Members on key areas. Any uncompleted assignments were progressing
well and those finalised following this meeting would be included in the Annual
Report at the next Committee meeting.
Ms.
Ashley-Caunt advised that at the time of reporting, a
further 4 audits had completed, as detailed at section 2.5 of the report.
·
Procurement
Compliance – This was an annual audit, whereby a sample of contracts awarded
during the last 12 months were reviewed to confirm if they had complied with
the Council's Contract Procedure Rules and if the Contracts Register was up to
date. In previous years, Internal Audit
had made a number of recommendations, particularly on retaining a good audit
trail to evidence the procurement process and the compliance with the key rules
and conditions. This year, compliance
with the Contract Procedure Rules was confirmed on all samples tested and only
minor issues, relating to sealing contracts and publishing award notices were
identified. This reflected the training
and awareness completed as a result of previous actions from audits over the
last few years. There were some areas of
the Contracts Register which needed to be developed and updated but as this was
a work in progress, no formal recommendations had been made. This would be reviewed again next year. No formal recommendations had been made on
Procurement Compliance and a good level of assurance overall had been issued.
·
Performance
and Risk Management Framework. Having reviewed the new Framework to check it
was robust and how it was being complied with in practice, Internal Audit were
satisfied. It was clear, concise,
covered all key areas and focused on the Council's Corporate Strategy. Internal Audit were also satisfied on the
coverage of the risk registers (Corporate and Directorate). There were no areas of concern on
Performance, which worked well, ensuring accountability and transparency on how
services were being delivered. There
were no formal recommendations and a good level of assurance was issued.
·
Covid-19
Recovery – This audit had been undertaken with all councils within the shared
internal audit service. Internal Audit
considered how the Council had responded to the pandemic (governance and
decision making) and how it recovered effectively (lessons learned, changes to
ways of working, business continuity plans links to general corporate and
service planning etc). There were no areas of concern, no formal
recommendations and Internal Audit had issued a substantial assurance opinion
(the highest of all councils in the shared service).
·
Project
Management – Having reviewed a sample of five projects to consider if the
Council's Project Management Framework was robust, covered all key areas and
how it was being applied in practice, Internal Audit was impressed with the
Framework. The Framework in place for
project management was aligned with PRINCE2 (internationally recognised
methodology, which many councils aspire to).
There was a good, effective and consistent audit trail of how the
projects had been managed and compliance was assessed easily due to the level
of documentation available. An area for
improvement was to ensure external advisers used the same methodology, to
ensure consistency across all projects including those using external
support. Whilst risk management was
being well embedded within the projects, there was not a clear link between the
Council's risk registers and the project risk registers, although, it was
evident escalated risks had been added to the Strategic Risk Register (there
was evidence in practice but not on the Framework and the procedures). There were no areas of concern but Internal
Audit had made recommendations to strengthen some of the controls. A substantial assurance opinion was issued on
the design for the very robust Framework and a good assurance opinion was
issued for compliance, based on the sample of projects reviewed.
Ms.
Ashley-Caunt highlighted the Implementation of Audit
Recommendations, as detailed at Appendix 3, confirming that 10 recommendations
had been implemented since the last Committee meeting. Of the overdue actions, 3 were high priority,
with 1 being over 3 months overdue (Effectiveness of Case Management Arrangements
2019-20). This was detailed at Appendix
4 and included current status and a revised completion date of date of 30
April.
During
discussion the following points were noted:
·
Members
noted the progress made and thanked staff for their work.
·
In
response to a concern raised over why all overdue actions were not detailed at
Appendix 4, the Chief Internal Auditor clarified that Appendix 4 detailed only
those high priority recommendations, which were overdue for implementation by 3
months or more. The 2 high priority
recommendation due within the last 3 months but not implemented would be
detailed in Appendix 4 if they reached over 3 months overdue.
·
The
Chief Internal Auditor clarified that the Compliance Assurances table detailed
the various assurance statements which Members could receive at the completion
of audit assignments. The audits
reported to Members at this meeting had all been of good or substantial
assurance.
·
The
Director for Corporate Services confirmed that the Intensive Housing Management
Service had been in place for a considerable time (and may have been termed
Supporting People previously). The
service was for those who were vulnerable and required additional support such
as a warden scheme etc.
·
The
Chair clarified that Internal Audit had completed its filed work and would
report findings but the Planning Service Review was still underway, although
temporarily paused.
RESOLVED
that
the report and
progress made by the Internal Audit team in the delivery of the Audit Plan be NOTED.
Supporting documents: