Cabinet:
1)
APPROVED
to Delegate Melton Borough Councils ICT function to Hinckley and Bosworth
Borough Council representing the best option following a full options
appraisal;
2)
APPROVED
the delivery model of Hinckley and Bosworth Borough Council providing an
insourced ICT service to operate from January 2022 for a period of 5 years ending
on 31st December 2026
3)
APPROVED
funding of £52k to cover the Council’s share of the one-off costs to support
implementation as identified in Paragraph 9.5 of the report of which £17k be added
to the capital programme (£10k 2020/21, £7k 2021/22) to be funded from revenue,
the remaining £35k to be revenue;
4) APPROVED to delegate authority to the Director for Corporate Services to agree the terms of the inter authority delegation agreement with Hinckley and Bosworth Borough Council;
5)
APPROVED
the Partnership Charter at Appendix 3 of the report.